Office Furniture Installation: What to Expect

Quick answer: Commercial office furniture installation usually covers receiving and staging the delivery, assembling workstations, desks and seating, anchoring tall storage, managing cables and removing packaging. Before install day, the space should be finished, power and data roughed in, and the building's freight elevator, loading dock and after-hours access booked. Even a mid-size office often takes more than one day to install, so schedule it before the movers and IT.

Office desks and chairs arranged in the Salt Creek showroom

Rachel Kimura's first office move had plenty of surprises, but the one she remembers best happened on a Saturday. The installation crew showed up at 8 a.m., as planned. So did another tenant's movers, who had booked the building's only freight elevator for the whole morning. By the time the crew got upstairs, half the day was gone, and the install that was supposed to take one day took three.

Most people picture installation the way Rachel did the first time: the furniture shows up, a crew puts it together, done.

Here's the detail that changes the plan. Commercial installation is a project of its own, with its own schedule, its own building rules and its own checklist. The crew is only as fast as the building lets them be.

“The crew is only as fast as the building lets them be.”

What Does Office Furniture Installation Include?

What should you expect the installer to handle? A full-service commercial installation typically includes:

  • Receiving and staging, so pieces arrive in the order they'll be built.
  • Assembly of workstations, desks, conference tables and seating.
  • Leveling and connecting workstations and runs of desks.
  • Anchoring tall storage and bookcases to the wall.
  • Cable management, routing power and data through the furniture.
  • Debris removal, including packaging and pallets.
  • A walkthrough and punch list of adjustments and missing parts.

Confirm in writing which of these your quote includes, especially debris removal and work outside normal hours.

How Do You Prepare the Space?

What has to be done before the crew arrives? More than most people expect.

Before Install Day

  • Construction, paint and flooring are finished, and the space is clean.
  • Power and data are roughed in where the floor plan shows them.
  • The building's rules are in hand: freight elevator reservations, loading dock hours, after-hours access, parking for the truck.
  • The building has the installer's certificate of insurance, if it requires one.
  • Floor and wall protection is planned for halls and elevators.
  • Every workstation and office is labeled to match the floor plan.

The Freight Elevator

This was Rachel's lesson. In a multi-tenant building, reserve the freight elevator in writing for every hour of the install, and confirm it again the week before.

“Rachel booked one Saturday for the install. Without the freight elevator, it took three days.”

How Long Does Office Furniture Installation Take?

Is there a rule of thumb? It depends on the number of workstations, how complex they are and how easy the building is to work in. A small office may take a day. A mid-size office with dozens of workstations, private offices and conference rooms often takes several days. Ask your installer for a schedule by area, and build it into your office relocation timeline before the movers and IT crews.

What Is BIFMA, and Why Does It Matter?

How do you know commercial furniture is built for an office? Look for products tested to industry standards. BIFMA, the commercial furniture industry's trade association, sponsors the development of standards that support safe and functional business and institutional environments. Ask whether the chairs, desks and storage you're considering are tested to BIFMA standards.

Commercial Vs Residential Furniture

Why not use home office furniture in a commercial office? Commercial pieces are generally built for many hours of use by many different people, with heavier frames, more adjustable seating and longer warranties for commercial use. Home office furniture is often designed for one person and lighter use. Our guide to how long commercial office furniture should last goes deeper.

“Commercial furniture is built for many hours a day and many different people. That's the difference you're paying for.”

What Happens After Installation?

What should you check before the team moves in? Walk every area with the installer and make a punch list: wobbly desks, misaligned panels, missing hardware, damaged finishes. Agree on a date to close the list, ideally within the first two weeks.

How Rachel Is Planning This Install

This time, Rachel's install is on the calendar before the movers. The freight elevator is reserved for every hour of the three install days, in writing, and the building has the crew's insurance certificate on file. A design consultant from our Gilbert Office showroom walked the space with her and the building manager so the crew knows exactly where the truck parks and which hallway to protect.

Plan Your Installation with Us

Visit our Gilbert Office showroom at 2757 S. Santan Village Pkwy., Suite 101, or call (480) 598-1900.

Filed Under

Frequently Asked Questions

What Does Office Furniture Installation Include?

Receiving and staging, assembly, leveling, anchoring tall storage, cable management, debris removal and a punch list walkthrough.

How Long Does It Take to Install Office Furniture?

A small office may take a day. A mid-size office often takes several days, depending on the furniture and the building.

What Is BIFMA Certified Furniture?

Furniture tested to standards developed under BIFMA, the commercial furniture industry's trade association, for safe and functional business environments.

Should Furniture Be Installed Before Moving into a New Office?

Yes. Install furniture before the movers and IT, so workstations are ready when people and equipment arrive.